Using a One-Handed Clock to Convey Project Goals

The "iron triangle" is a long-accepted way of talking about the four parameters of project success. In the iron triangle, scope, schedule and budget each takes its place along a side of the triangle. Quality is placed in the middle under the premise that we don't mess with quality. We can, however, adjust the sides. Sometimes a product owner or key stakeholder is told, "Pick any two but I can adjust the third" by the project manager, ScrumMaster or coach. Sometimes the customer is told, "you can only lock down one of the sides." I've recently decided there's a better way to convey the points we've been trying to make with the iron triangle--we use The One-Handed Clock of Project Goals. To use the one-handed clock, position Scope, Schedule and Budget where twelve o'clock, four o'clock, and eight o'clock would be on a clock. It doesn't matter which is positioned where but I put them as shown in the figure. Quality is again assumable fixed and not needed on the clock.

The one-handed clock before its hand is added.

Next, ask the product owner or key stakeholder to point the one hand where it best indicates the project's goals. The one hand can be aimed, for example, directly at Schedule. This would indicate that Schedule is the most important goal and Scope and Budget both take a back seat to it.

A one-handed clock.

Or perhaps the one hand is pointed between Scope and Schedule showing a mix of importance between them.

1HandedClock-B

To see how the One-Handed Clock of Project Goals works, take a moment to think about it. You can position the hand anywhere between any two of three goals but one goal is always left out. In the terms of the iron triangle, that would be the side left flexible. There are a lot of things I like about this new way of visualizing the relative importance of Scope, Schedule and Budget. I'll mention two here:

  • The One-Handed Clock allows stakeholders or product owners to convey a position more precisely than saying something like "I pick Schedule and Budget." The ability to point the arrow precisely rather than only directly at an item is essential.
  • The One-Handed Clock is a useful visual metaphor that can be hung in a team room. The iron triangle doesn't really work for that as it's hard to convey which sides were selected other than by darkening them, which doens't show much.

Try this out and let me know what you think. The teams and product owners I've introduced it to so far have found it to be a very helpful agile project management tool. I suspect you will as well. Also, let me know what else you use a one-handed clock for as it's a useful visualization for any three competing factors.


Download Scrum Master Guide

Download Scrum Master Guide

Get a free copy of Situational Scrum Mastering: Leading an Agile Team

Get my free guide now!
38

Posted:

Mike Cohn

About the Author

Mike Cohn specializes in helping companies adopt and improve their use of agile processes and techniques to build extremely high-performance teams. He is the author of User Stories Applied for Agile Software Development, Agile Estimating and Planning, and Succeeding with Agile as well as the Better User Stories video course. Mike is a founding member of the Agile Alliance and Scrum Alliance and can be reached at hello@mountaingoatsoftware.com. If you want to succeed with agile, you can also have Mike email you a short tip each week.

The discussion here is closed but join us in the Agile Mentors Community to further discuss this topic.

Go to AgileMentors.com